Page 20Scan 41 of 126
Sunday 25 September Rest day. Various works at the camp. Storm with heavy rain at noon -
Monday 26 September 6th day of the excavation. Continuation of the clearing of pits.
Continuation of the architectural recording with the help of a young man recently hired.
Staff = area = 4 men 1 boy (recording) 9 women. House = 1 woman -
A new woman was hired on the site, because the washing of the sherds took one of the 8 we had previously.
65 figures hard to readstruck struck outadded written in above” jug ditto, and what it repeatsword reading not certain